  • 1. Enshassi, A., Al-Hallaq, K., and Mohamed, S. (2006). Causes of Contractor’s Business Failure in Developing Countries: The Case of Palestine, Journal of Construction Developing Countries, 11(2), 1– 14. 2. Akogbe, R.K.T., Feng, X., Zhou, J., 2013. Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering. 17 (6):1213-1222. 3. Olbak M ., Naimi, S. (2016). Kentsel Dönüşüm Uygulanmış 5 Katlı İki Yapı Örneğinin Deneysel Verileri Kullanılarak Doğrusal Olmayan Analiz Yöntemleri İle Güçlendirme Sonuçlarının İrdelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (3), 145-166. 4. Mahamid, 2011. Common Risks Affecting Time Overrun in Road Construction Projects in Palestine: Contractors’ Perspective, Australasian Journal Construction Economics Building this, vol. 13, no. 2, pp.45–53, 2011. 5. Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A., 2012. Causes of Delays in Construction Projects in Turkey, Journal of Civil Engineering and Management, 2012, 18(3): 426-435. 6. Marzouk, M.M. and El-Rasas, T.I., 2014, Analyzing delay causes in Egyptian construction projects, Journal of Advanced Research, Vol. 5 No.1, pp.49-55. 7. Trauner, J.T., Manginelli, W.A., Lowe, J.S., Nagata, M.F., Furniss, B.J., 2009. Construction Delays: understanding them clearly and Delay Analysis in Construction Analyzing them correctly. 8. Faridi, A.S., El-Sayegh, S.M., 2006. Significant factors causing delay in the UAE construction industry. Construction Management and Economics 24 (11):1167–1176. 9. Odeyinka, H.A. and Yusif, A., 1997, The causes and effects of construction delays on completion cost of housing projects in Nigeria, Journal of Financial Management of Property and Construction 1997, 2(3), 31-44. 10. Sambasivan M., Soon Y. W., 2007. Causes and Effects of Delays in Malaysian Construction İndustry, International Journal of Project Management 25 (2007) 517-526. 11. Zidane, Y.J-T., Andersen, B. 2018. The Top 10 Universal Delay Factors in Construction Projects, International Journal of Managing Projects in Business, Vol. 11 Issue: 3, pp.650-672. 12. Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in Indian construction projects, International Journal of Project Management 30 (2012) 479–489. 13. Sunjka, B.P., Jacob, U. 2013. Significant causes and effects of project delays in the Niger Delta region, Nigeria, SAIIE25 Proceedings, 9th – 11th of July 2013, Stellenbosch. 14. Almutairi, N.S., 2016. Causes pf delays on construction projects in Kuwait according to opinion of engineers working in Kuwait, International Journal of Engineering Research and Application, ISSN: 2248-9622, Vol.6, Issue 12, (Part-3) December 2016, pp 84-96. 15. Rezaei, A., Jalal, S.,2018. Investigating the causes of delay and cost-overrun in construction industry, International Advanced Researches and Engineering Journal 02(02): 075-079, 2018. 16. Reihanifar M ., Naimi, S. (2016). Proje ve Maliyet Yönetimi Yöntemleriyle Kalitenin ve Verimliliğin Artırılmasının İncelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (29), 51-65. 17. Reihanifar M ., Naimi, S. (2016). Evaluatıon of Road Constructıon Projects by Value Engıneerıng Approach as a Tool for Sustainability. International journal of ecosystems and ecology science (IJEES), 8 (2), 339-346. 18. Gülce, A.C., 2010. Veri Madenciliğinde Apriori Algoritması ve Apriori Algoritmasının Farklı Veri Kümelerinde Uygulanması, Trakya Üniversitesi Fen Bilimleri Enstitüsü, Bilgisayar Mühendisliği Ana Bilim Dalı, Yüksek Lisans Tezi. 19. Liao, C.W. and Perng, Y.H., 2007. Data mining for occupational injuries in the Taiwan construction industry. Safety Science, 46, 1091-1102. 20. Tsay, Y.J., Chiang, J.Y., 2005. CBAR: an efficient method for mining association rules. KnowledgeBased Systems 18, 99–105 21. Erpolat, S., 2012. Comparison of Apriori and FP-Growth Algorithms on Determination of Association Rules in Authorized Automobile Service Centres, Anadolu University Journal of Social Sciences, Vol. 12 No:1 (151-166) 137-146. 22. Sıramkaya, E., 2005. Veri Madenciliğinde Bulanık Mantık Uygulaması, Selçuk Üniversitesi, Fen Bilimleri Enstitüsü Yüksek Lisans Tezi. 23. Kılınç, Y., 2009. Mining Association Rules For Quality Related Data In An Electronics Company, Middle East Technical University, Industrial Engineering. 24. Doğrul, G., Akay, D., Kurt, M., 2015. Analysis of Traffic Accidents by Rules of Association, Gazi Journal of Engineering Sciences, 1/2 (2015) 265-284. 25. Söylemez, İ., Doğan A. and Özcan, U., 2016. Association Rules on Traffic Accident: Case of Ankara, Ege Academic Review, Cilt 16, Özel Sayı, 2016 ss. 11/20.

Discovering hidden patterns in Turkish construction projects delays related to project characteristic

Year 2019, Volume: 4 Issue: 2, 372 - 378, 21.10.2019
https://doi.org/10.29187/jscmt.2019.41

Abstract

There are delays in delivering construction projects, which have great affects in all countries' economies, due to many factors
and reasons and these delays bring many negative consequences. Checking the source of these consequences or minimizing
their effects is very important in terms of time and cost savings in the construction sector, especially for countries which have
a continuous improvement such as Turkey. Determination of project factors that will cause delay, analysis of their impacts
and taking protective measures will help to reduce losses. Hereby in this study, the project factors that may cause to delays
are identified and some important association rules between these factors and delay are extracted by collecting the data from
Turkish Public and private construction projects. Also, some recommendations were presented for reducing delays by using
the extracted rules. 

References

  • 1. Enshassi, A., Al-Hallaq, K., and Mohamed, S. (2006). Causes of Contractor’s Business Failure in Developing Countries: The Case of Palestine, Journal of Construction Developing Countries, 11(2), 1– 14. 2. Akogbe, R.K.T., Feng, X., Zhou, J., 2013. Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering. 17 (6):1213-1222. 3. Olbak M ., Naimi, S. (2016). Kentsel Dönüşüm Uygulanmış 5 Katlı İki Yapı Örneğinin Deneysel Verileri Kullanılarak Doğrusal Olmayan Analiz Yöntemleri İle Güçlendirme Sonuçlarının İrdelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (3), 145-166. 4. Mahamid, 2011. Common Risks Affecting Time Overrun in Road Construction Projects in Palestine: Contractors’ Perspective, Australasian Journal Construction Economics Building this, vol. 13, no. 2, pp.45–53, 2011. 5. Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A., 2012. Causes of Delays in Construction Projects in Turkey, Journal of Civil Engineering and Management, 2012, 18(3): 426-435. 6. Marzouk, M.M. and El-Rasas, T.I., 2014, Analyzing delay causes in Egyptian construction projects, Journal of Advanced Research, Vol. 5 No.1, pp.49-55. 7. Trauner, J.T., Manginelli, W.A., Lowe, J.S., Nagata, M.F., Furniss, B.J., 2009. Construction Delays: understanding them clearly and Delay Analysis in Construction Analyzing them correctly. 8. Faridi, A.S., El-Sayegh, S.M., 2006. Significant factors causing delay in the UAE construction industry. Construction Management and Economics 24 (11):1167–1176. 9. Odeyinka, H.A. and Yusif, A., 1997, The causes and effects of construction delays on completion cost of housing projects in Nigeria, Journal of Financial Management of Property and Construction 1997, 2(3), 31-44. 10. Sambasivan M., Soon Y. W., 2007. Causes and Effects of Delays in Malaysian Construction İndustry, International Journal of Project Management 25 (2007) 517-526. 11. Zidane, Y.J-T., Andersen, B. 2018. The Top 10 Universal Delay Factors in Construction Projects, International Journal of Managing Projects in Business, Vol. 11 Issue: 3, pp.650-672. 12. Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in Indian construction projects, International Journal of Project Management 30 (2012) 479–489. 13. Sunjka, B.P., Jacob, U. 2013. Significant causes and effects of project delays in the Niger Delta region, Nigeria, SAIIE25 Proceedings, 9th – 11th of July 2013, Stellenbosch. 14. Almutairi, N.S., 2016. Causes pf delays on construction projects in Kuwait according to opinion of engineers working in Kuwait, International Journal of Engineering Research and Application, ISSN: 2248-9622, Vol.6, Issue 12, (Part-3) December 2016, pp 84-96. 15. Rezaei, A., Jalal, S.,2018. Investigating the causes of delay and cost-overrun in construction industry, International Advanced Researches and Engineering Journal 02(02): 075-079, 2018. 16. Reihanifar M ., Naimi, S. (2016). Proje ve Maliyet Yönetimi Yöntemleriyle Kalitenin ve Verimliliğin Artırılmasının İncelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (29), 51-65. 17. Reihanifar M ., Naimi, S. (2016). Evaluatıon of Road Constructıon Projects by Value Engıneerıng Approach as a Tool for Sustainability. International journal of ecosystems and ecology science (IJEES), 8 (2), 339-346. 18. Gülce, A.C., 2010. Veri Madenciliğinde Apriori Algoritması ve Apriori Algoritmasının Farklı Veri Kümelerinde Uygulanması, Trakya Üniversitesi Fen Bilimleri Enstitüsü, Bilgisayar Mühendisliği Ana Bilim Dalı, Yüksek Lisans Tezi. 19. Liao, C.W. and Perng, Y.H., 2007. Data mining for occupational injuries in the Taiwan construction industry. Safety Science, 46, 1091-1102. 20. Tsay, Y.J., Chiang, J.Y., 2005. CBAR: an efficient method for mining association rules. KnowledgeBased Systems 18, 99–105 21. Erpolat, S., 2012. Comparison of Apriori and FP-Growth Algorithms on Determination of Association Rules in Authorized Automobile Service Centres, Anadolu University Journal of Social Sciences, Vol. 12 No:1 (151-166) 137-146. 22. Sıramkaya, E., 2005. Veri Madenciliğinde Bulanık Mantık Uygulaması, Selçuk Üniversitesi, Fen Bilimleri Enstitüsü Yüksek Lisans Tezi. 23. Kılınç, Y., 2009. Mining Association Rules For Quality Related Data In An Electronics Company, Middle East Technical University, Industrial Engineering. 24. Doğrul, G., Akay, D., Kurt, M., 2015. Analysis of Traffic Accidents by Rules of Association, Gazi Journal of Engineering Sciences, 1/2 (2015) 265-284. 25. Söylemez, İ., Doğan A. and Özcan, U., 2016. Association Rules on Traffic Accident: Case of Ankara, Ege Academic Review, Cilt 16, Özel Sayı, 2016 ss. 11/20.
There are 1 citations in total.

Details

Primary Language English
Subjects Civil Engineering
Journal Section Research Articles
Authors

İsmail Cengiz Yılmaz

Publication Date October 21, 2019
Submission Date September 12, 2019
Acceptance Date October 14, 2019
Published in Issue Year 2019 Volume: 4 Issue: 2

Cite

APA Yılmaz, İ. C. (2019). Discovering hidden patterns in Turkish construction projects delays related to project characteristic. Journal of Sustainable Construction Materials and Technologies, 4(2), 372-378. https://doi.org/10.29187/jscmt.2019.41

Cited By

Assessment of Risks in Building Inspection Services during and Post-COVID-19 Pandemic
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
https://doi.org/10.1061/AJRUA6.0001214

88x31_3.png

Journal of Sustainable Construction Materials and Technologies is open access journal under the CC BY-NC license  (Creative Commons Attribution 4.0 International License)

Based on a work at https://dergipark.org.tr/en/pub/jscmt

E-mail: jscmt@yildiz.edu.tr